Procurement Act 2023 Roadmap
Lifecycle compliance guide, statutory notice rules engine (UK1–UK8), 8-working-day standstill calculator, and interactive supplier readiness assessment.
Procurement Lifecycle Phases & Notice Triggers
Pre-Market Planning & Pipeline Transparency
Statutory 18-month forward pipeline visibility under Section 93
Contracting authorities with total annual procurement budgets exceeding £100m must publish Pipeline Notices (UK1) for upcoming public contracts valued over £2m expected in the next 18 months.
Mandatory Requirements
- Mandatory publication of UK1 Pipeline Notices for procurements >£2m.
- Duty to consider SME participation and barriers to entry early.
- Integration with the UK Central Digital Platform for single-register supplier credentials.
Procurements valued over £2,000,000 (inc. VAT) published by authorities with >£100m annual spend.
Not applicable at Stage 1 (Forward planning phase).
Standstill Period Calculator (Section 51)
Calculate Statutory 8-Working-Day Standstill Window
Under the UK Procurement Act 2023, contracting authorities must observe a mandatory standstill period of at least 8 working days starting the day after Contract Award Notice (UK6) publication.
Organizational Self-Assessment
Procurement Act 2023 Readiness Scorecard
Procurement Act 2023 Compliance & Transition Roadmap — Statutory lifecycle guide, standstill calculator, and supplier readiness scorecard.